Skip to main content

Southtowns Advanced Wastewater Treatment Facility Expansion Project Update

Southtowns Advanced Wastewater Treatment Facility Expansion Project
Phase 1 Construction Update (September 2024)

Notice to proceed for Phase 1 of the Southtowns Advanced Wastewater Treatment Facility Expansion Project was issued in December 2023, with the contractor mobilizing onsite soon after.  Construction is approximately one-third complete as of September 2024.

The progress thus far includes: 

  • Electrical substation: approximately 75% of the building structure is complete; the majority of the conduits and duct banks to the substation installed; long-lead time items such as the generator, switchgear, and other equipment have been ordered (with some already delivered).
  • Effluent submersible pumping station: excavation has been performed and temporary sheeting/shoring systems installed; the majority of below grade concrete structures have been completed and tested; long-lead time items such as the pumps and associated equipment have been ordered; discharge piping is onsite and ready to be installed.
  • Chlorine contact tank: excavation has been performed, all support piles have been installed; approximately 50% of the concrete floor slab and the effluent chamber walls have been poured; steel rebar and concrete form work for the remainder of the structure is in progress.
  • Effluent piping: major structures have been ordered and are onsite; interconnections between existing 66โ€ diameter piping and new piping have been excavated and prepared for installation; outfall diffuser repairs within the lake are complete.
  • Site work: access roads, site grading, and other features completed throughout the site.

Below are aerial photos showing the progress of various components of the project. 

Site Overview (facing southwest)

Site Overview (Facing Southwest)
New electrical building (left) and effluent pumping station (center) facing southeast

New electrical building [left] and effluent submersible pumping station [center] (facing southeast)
New chlorine tank

New chlorine contact tank (facing southwest)
new chlorine tank (facing south)

New chlorine contact tank (facing south)
existing 66" piping

Existing 66" diameter piping being prepared for a new connection (location #1, facing south)
Existing 66โ€ diameter piping being prepared for a new connection (location #2, facing southeast)

Existing 66โ€ diameter piping being prepared for a new connection (location #2, facing southeast)

For more information on the Southtowns Advanced Wastewater Treatment Facility Expansion Project, please visit: Southtowns Advanced Wastewater Treatment Facility Expansion Project | Division of Sewerage Management (DSM) (erie.gov)

Changed