Skip to main content

Black Rock Canal Park Capital Improvements

2012 - 2024 Capital Improvements:

Project Name Type of Work Completed Estimated Cost to Complete
BRCP Development  Multi-Phase Projects to redesign Park includes adding a Dog Park, Maintenance Building, Improve Parking, Site Work Amenities, Signage, etc.  $1,800,000.00
Dock Safety-Related Concerns  Investigation of the dock at BRCP suggested blocking off for public access until replaced. Vendor fenced/blocked off dock area assuring public cannot gain access until Phase 2 is completed. $2,150.00

 

TOTAL:

$1,802,150.00