Skip to main content

Bureau of Forestry Capital Improvements

2012 - 2024 Capital Improvements:

Project Name Type of Work Completed Estimated Cost to Complete
New Water System Water at the Forestry building wasn't potable. Installed a new water system. $3,150.00
Building Renovations Metal roofs/fascia replaced on five (5) structures. $55,367.00
New Vacuum Pump System Maple syrup production upgrade. $11,380.00
Forestry Management Plan Updating the 2003 Forestry Management Plan $149,370.00
Parking Lot Improvements Repaved parking lot. $9,875.00

 

TOTAL:

$229,142.00